| PROJECT |
CONSTRUCTION, ERECTION & PRE-COMMISSIONING OF ESFAHAN LUBE OIL COMPLEX |
| LOCATION |
ESFAHAN / IRAN |
| CLIENT/OWNER |
NIOC- NIOPDC (National Iranian Products and Distribution Co.) |
| MANAGING CONTRACTOR (MC) |
OIEC |
| CONTRACT EFFECTIVE DATE |
MARCH 1989 |
| CONTRACT DURATION |
33 months |
| BUDGETED man-hours |
4,200,000 man-hours |
| EXPENDED man-hours |
4,050,000 man-hours (REV.12) |
| PROGRESS STATUS |
COMPLETED (MARCH 92) |
Scope of Work
Execution of construction, erection and pre-commissioning of Esfahan Lube Oil Complex with a capacity of 184,000 metric tons annually.
Major items of this project were
| Excavation |
268,000 m3 |
| Rebar Work |
3,000 tons |
| Form Work |
48,000 m2 |
| Concrete Casting |
48,200 m3 |
| Construction of Buildings |
35,000 m2 |
| Construction and Erection of Steel Structure |
2,200 tons |
| Road Construction |
45,000 m2 |
| Concrete Paving |
100,000 m2 |
| Installation of Instruments andEquipment |
4,200 tons |
| |
|
prefabrication and Installation of
| A/G Piping |
2450 tons |
| U/G Piping |
1150 tons 40,000 meters (m) |
| Cement and CastIron Piping |
17,000 length. meters (l.m) |
| |
|
Electrical Works included
| Cabling |
190 km |
| Wiring |
150 km |
| Conduit |
50 km |
| |
|
Installation of Instrumentation and control included
Insulation and Painting included
| Insulation |
35,000 m2 |
| Painting |
60,000 m2 |
| |
|
Number of Direct Man Power at Peak in This Project was: 900
LAB COMPLEX FEED FACILITIES
| PROJECT |
LAB COMPLEX FEED FACILITIES |
| LOCATION |
ESFAHAN / IRAN |
| CLIENT |
IRAN CHEMICAL INDUSTRY INVESTMENT CO. |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
AUGUST 1992 |
| CONTRACT DURATION |
15 months (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
620,000 man-hours |
| EXPENDED man-hours |
650,000 man-hours (REV. 12) |
| PROGRESS STATUS |
COMPLETED (NOVEMBER 1993) |
| |
|
| |
|
Scope of Works
- Construction of the Feed Facilities
- Erection and Commissioning of Interconnecting Systems
Major Works
| Excavation |
30,000 m3 |
| Rebar Work |
200 tons |
| Form Work |
5,100 m2 |
| Concrete Casting |
4,150 m3 |
| Fabrication and Erection of Steel Structure |
42 tons |
| Equipment Erection |
850 tons |
| A/G Piping |
104,000 inch meters (in-m) |
| U/G Piping |
24,000 inch meters (in-m) |
| Electrical Cabling |
20,000 meters (m) |
| Instrumentation Cabling |
15,000 meters (m) |
| Painting of Equipment |
15,900 m2 |
Number of Direct Man Power at Peak in this Project was: 120
ESFAHAN PETROCHEMICAL COMPLEX - FEED FACILITIES
| PROJECT |
ESFAHAN PETROCHEMICAL COMPLEX - FEED FACILITIES |
| LOCATION |
ESFAHAN / IRAN |
| CLIENT |
ESFAHAN PETROCHEMICAL COMPANY |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
APRIL 1992 |
| CONTRACT DURATION |
20 months (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
55,000 man-hours |
| EXPENDED man-hours |
170,000 man-hours (REV. 12) |
| PROGRESS STATUS |
COMPLETED (APRIL 1993) |
| |
|
Scope of Work
Construction, Installation and Commissioning of Feed Facilities with a capacity of 184,000 metric tons yearly.
Major Items of this Project are:
| Excavation |
9,105 m3 |
| Rebar Work |
160,600 kg |
| Form Work |
4,716 m2 |
| Concrete Casting |
1,350 m3 |
| A/G & U/G Piping |
109,000 inch meters (in-m) |
| Painting of Pipes |
30,000. m2 |
| |
|
Number of direct man power at peak in this project was: 50
|