South Pars Gas Field Development - Phases 9 and 10
NGL 1200, 1300
Amir Kabir Petrochemical Complex
Sixth Olefin Plant
Bandar Abbas Refinery
Gas Compressor Stations S1, S2, S3, S6
» Karanj - NGL 1500
Karanj Parsi - CS 600, 700
Tabriz Petrochemical Complex
Khorasan Petrochemical Complex
Esfahan Lube Oil Complex
Sirri Island Gas Gathering and NGL Recovery
Karanj - NGL 1500


LOCATION  KHUZESTAN PROVINCE/ IRAN
CLIENT NIOC ONSHORE 
CONTRACTOR OIEC
CONTRACT EFFECTIVE DATE  November 21st, 1996
CONTRACT DURATION 33 months (INCLUDING 2 months FOR   MOBILIZATION)
BUDGETED man-hours  792,000 man-hours
EXPENDED man-hours 2,827,736 man-hours
PROGRESS STATUS COMPLETED (MARCH 21, 1999)


Scope of Work

Construction and Erection of NGL Unit 1500 and related facilities (Natural Gas Liquid Factory), covering the following activities:

- Mobilization
- Civil Work
- Concrete Work
- Steel Structure
- Mechanical Equipment of Building
- Piping
- Equipment Erection
- Client Ordered Facilities
- Demobilization


Major items of this Project were

Excavation 42,647 m3
Rebar Work 1,600 tons
Form Work 44,200 m2
Concrete Casting 22,400 m3
Steel Structure 965 tons
Equipment Erection 1,100 tons
Welding 126,860 inch diameter


Number of Direct Man Power at Peak in this Project was: 350


In order& to provide a part of the required feed of Bandar Emam Petrochemical Compress (BIPC), the design and construction of NGL Unit 1500 and related facilities was implemented.

The plant treats the associated sour rich gases and the final products of this plant are sweet condensate gas (NGL) as feed of BIPC and lean gas for injection to oil reservoirs with following volumes per day :


1- NGL: 38,400 bbl/d
2- Lean gas: 243,000,000 SCFD (6,881,000 Sm3/d)



Home | About Us | Services | Projects | Subsidiaries | Join Us | Contact Us