| Karanj - NGL 1500 |
|
| LOCATION |
KHUZESTAN PROVINCE/ IRAN |
| CLIENT |
NIOC ONSHORE |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
November 21st, 1996 |
| CONTRACT DURATION |
33 months (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
792,000 man-hours |
| EXPENDED man-hours |
2,827,736 man-hours |
| PROGRESS STATUS |
COMPLETED (MARCH 21, 1999) |
Scope of Work
Construction and Erection of NGL Unit 1500 and related facilities (Natural Gas Liquid Factory), covering the following activities:
- Mobilization
- Civil Work
- Concrete Work
- Steel Structure
- Mechanical Equipment of Building
- Piping
- Equipment Erection
- Client Ordered Facilities
- Demobilization
Major items of this Project were
| Excavation |
42,647 m3 |
| Rebar Work |
1,600 tons |
| Form Work |
44,200 m2 |
| Concrete Casting |
22,400 m3 |
| Steel Structure |
965 tons |
| Equipment Erection |
1,100 tons |
| Welding |
126,860 inch diameter |
Number of Direct Man Power at Peak in this Project was: 350
In order& to provide a part of the required feed of Bandar Emam Petrochemical Compress (BIPC), the design and construction of NGL Unit 1500 and related facilities was implemented.
The plant treats the associated sour rich gases and the final products of this plant are sweet condensate gas (NGL) as feed of BIPC and lean gas for injection to oil reservoirs with following volumes per day :
1- NGL: 38,400 bbl/d
2- Lean gas: 243,000,000 SCFD (6,881,000 Sm3/d)
|