KARANJ GAS COMPRESSION & INJECTION STATION CS- 600
| LOCATION |
KHUZESTAN PROVINCE/ IRAN |
| CLIENT |
NIOC ONSHORE |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
AUGUST 1995 |
| CONTRACT DURATION |
31 months (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
1,100,000 man-hours; 1,407,781 man-hours (FINAL REV) |
| EXPENDED man-hours |
1,355,000 man-hours (Direct); 1,987,300man-hours (Overall) |
| PROGRESS STATUS |
COMPLETED (FEBRUARY 1998) |
Scope of Work
Construction of Gas Compressor Station CS 600 and related facilities for Injection of 500 million SCF/D (14.2 MSm3/d) Gas to KARANJ Reservoir for Pressure Maintenance and Oil Recovery.
This included :
- Mobilization
- Civil Work
- Building & Shelter
- Erection of Compressor Unit, Equipment & Piping
- Electrical & Instrumentation
- Paint & Insulation
- Test & Pre-commissioning
- Procurement & Transportation of Materials
Major items of this Project were
| Excavation | 81,900 m3 |
| Rebar Work | 871 tons |
| Form Work | 34,000 m2 |
| Concrete Casting | <16,250 m3/td> |
| Steel Structure | 735 tons |
| Equipment Erection | 1,011 tons |
| Piping | 48,800 inch diameter |
Number of Direct Man Power at Peak in this Project was: 450
» PARSI GAS COMPRESSION & INJECTION STATION CS-700
| LOCATION |
KHUZESTAN PROVINCE / IRAN |
| CLIENT |
NIOC ONSHORE |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
NOVEMBER 21, 1996 |
| CONTRACT DURATION |
33 months, extended to 52 months (Inclusive Additional Works for Living, Recreation and Utilities Facilities for the Personnel of the Stations CS-600 and CS-700 (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
1,860,000 man-hours |
| EXPENDED man-hours |
2,300,000 man-hours plus 1,427,250 man-hours for Additional Work |
| PROGRESS STATUS |
COMPLETED (MARCH 21, 2001) |
Scope of Work
Construction of Gas Compressor Station CS 700 and related facilities for Injection of 400 million SCF/D (11.3 MSm3 /d) Gas to PARSI Reservoir for Pressure Maintenance and Oil Recovery, covering the following activities:
- Mobilization
- Civil Work
- Buildings Structure
- Buildings Architecture
- Buildings Mechanical
- Erection of Rotary Equipment & Static Equipment
- Piping (U/G & A/G)
- Electrical & Instrumentation
- Pre-commissioning
- Client Ordered Facilities
- Client Camp Demobilization
Major items of this Project were
| Excavation & Transportation | 41,300 m3 |
| Rebar Work | 774 tons |
| Form Work | 33,400 m2 |
| Concrete Casting | 16,200 m3 |
| Steel Structure | 783 tons |
| U/G Piping | 5,800 inch diameter |
| A/G Piping | 56,400 inch diameter |
| Equipment Erection | 700 tons |
| Welding | 62,200 inch diameter |
Number of Direct Man Power at Peak in this Project was: 300
|