Oil Industries’ Engineering and Construction (OIEC)
Projects
Projects

Ongoing Projects

Completed Projects

South Pars Gas Field Development - Phases 9 and 10
NGL 1200, 1300
Amir Kabir Petrochemical Complex
Sixth Olefin Plant
Bandar Abbas Refinery
Gas Compressor Stations S1, S2, S3, S6
Karanj - NGL 1500
» Karanj Parsi - CS 600, 700
Tabriz Petrochemical Complex
Khorasan Petrochemical Complex
Esfahan Lube Oil Complex
Sirri Island Gas Gathering and NGL Recovery
 Karanj Parsi - CS 600, 700

KARANJ GAS COMPRESSION &  INJECTION STATION CS- 600

LOCATION  KHUZESTAN PROVINCE/ IRAN
CLIENT NIOC ONSHORE
CONTRACTOR OIEC
CONTRACT EFFECTIVE DATE  AUGUST 1995
CONTRACT DURATION 31 months (INCLUDING 2 months FOR MOBILIZATION)
BUDGETED man-hours  1,100,000 man-hours; 1,407,781 man-hours (FINAL REV)
EXPENDED man-hours 1,355,000 man-hours (Direct); 1,987,300man-hours (Overall)
PROGRESS STATUS COMPLETED (FEBRUARY 1998)


Scope of Work

Construction of Gas Compressor Station CS 600 and related facilities for Injection of 500 million SCF/D (14.2   MSm3/d) Gas to KARANJ Reservoir for Pressure Maintenance and Oil Recovery.

This included :

- Mobilization
- Civil Work
- Building & Shelter
- Erection of Compressor Unit, Equipment & Piping
- Electrical & Instrumentation
- Paint & Insulation
- Test & Pre-commissioning
- Procurement & Transportation of Materials

Major items of this Project were


Excavation81,900 m3
Rebar Work871 tons
Form Work34,000 m2
Concrete Casting<16,250 m3/td>
Steel Structure735 tons
Equipment Erection1,011 tons
Piping48,800 inch diameter

Number of Direct Man Power at Peak in this Project was: 450


» PARSI GAS COMPRESSION & INJECTION STATION CS-700

LOCATION KHUZESTAN PROVINCE / IRAN
CLIENT NIOC ONSHORE 
CONTRACTOR OIEC
CONTRACT EFFECTIVE DATE NOVEMBER 21, 1996
CONTRACT DURATION 33 months, extended to 52 months (Inclusive   Additional Works for Living, Recreation and Utilities Facilities for the Personnel of the Stations CS-600 and CS-700      (INCLUDING 2 months FOR   MOBILIZATION)
BUDGETED man-hours  1,860,000 man-hours
EXPENDED man-hours 2,300,000 man-hours plus 1,427,250 man-hours for Additional Work
PROGRESS STATUS COMPLETED (MARCH 21, 2001)

                                                                        
Scope of Work

Construction of Gas Compressor Station CS 700 and related facilities for Injection of 400 million SCF/D (11.3 MSm3 /d) Gas to PARSI Reservoir for Pressure Maintenance and Oil Recovery, covering the following activities:

- Mobilization
- Civil Work
- Buildings Structure
- Buildings Architecture
- Buildings Mechanical
- Erection of Rotary Equipment & Static Equipment
- Piping (U/G & A/G)
- Electrical & Instrumentation
- Pre-commissioning
- Client Ordered Facilities
- Client Camp Demobilization

Major items of this Project were


Excavation & Transportation41,300 m3
Rebar Work774 tons
Form Work33,400 m2
Concrete Casting16,200 m3
Steel Structure783 tons
U/G Piping5,800 inch diameter
A/G Piping56,400 inch diameter
Equipment Erection700 tons
Welding62,200 inch diameter

Number of Direct Man Power at Peak in this Project was: 300