| Tabriz Petrochemical Complex |
|
- RAW WATER/ DEMINERALIZED WATER/ ANTS.
- CIVIL AND CONSTRUCTION WORK OF AREA “C1” OF PRODUCTION LINE“C”/
UNIT 21 OF ETHYL BENZENE AND UNIT 22 OF STYRENE MONOMER UNITS.
» TABRIZ PETROCHEMICAL COMPLEX- RAW WATER/DEMINERALIZED WATER/POTABLE WATER TREATMENT
| LOCATION |
TABRIZ / IRAN |
| CLIENT |
TABRIZ PETROCHEMICAL COMPANY |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
SEPTEMBER 1995 |
| CONTRACT DURATION |
16.5 months (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
226,000 man-hours |
| EXPENDED man-hours |
416,000 man-hours |
| PROGRESS STATUS |
COMPLETED (JANUARY 1997) |
| |
|
Scope of Work
- Erection of Mechanical Equipment
- Installation of A/G Piping
- Electrical Work
- Instrumentation
- Painting & Insulation
- Pre-commissioning
Major items of this Project were:
|
Erection of Mechanical Equipment |
534 tons |
|
Insulation |
2,873 m2 |
|
Electrical & Instrumentation (Cabling) |
76,000 l.m(length-meters) |
|
Fabrication of Carbon Steel Pipes |
14,000 inch diameter |
|
Erection of Carbon Steel Pipes |
13,000 inch diameter |
|
Fabrication of Stainless Steel Pipes |
13,000 inch diameter |
|
Erection of Stainless Steel Pipes |
7,500 inch diameter |
|
Electrical Plates |
35 units |
|
Instrumentation Devices |
410 units |
|
Painting |
5,085 m2 |
Number of Direct Man Power at Peak in this Project was: 200
» TABRIZ PETROCHEMICAL COMPLEX-CIVIL AND CONSTRUCTION WORK OF AREA “C1” OF PRODUCTION LINE “C”/UNIT 21 ETHYL BENZENE AND UNIT 22 STYRENE MONOMER UNITS
| LOCATION |
TABRIZ / IRAN |
| CLIENT |
TABRIZ PETROCHEMICAL COMPANY |
| CONTRACTOR |
OIEC |
| CONTRACT EFFECTIVE DATE |
JULY 1994 |
| CONTRACT DURATION |
43 months (INCLUDING 2 months FOR MOBILIZATION) |
| BUDGETED man-hours |
1,814,540 man-hours |
| EXPENDED man-hours |
3,700,580 man-hours (Direct); 4,972,760 man- hours (Overall) |
| PROGRESS STATUS |
COMPLETED (MARCH 1998) |
| |
|
Scope of Work:
- Erection of Mechanical Equipment
- Installation of A/G Piping
- Electrical Work
- Instrumentation
- Painting & Insulation
- Pre-commissioning
Major items of this Project were
- Excavation = 52,000 m3
- Reinforced Concrete Work = 13,000 m3
- Fabrication and Erection of Steel Structure = 1,050 tons
- Erection of Mechanical Equipment = 2,200 tons
- Instrumentation (Cabling & Control) = 133 km
- A/G Piping Erection = 150,000 inch meter (in-m)
- A/G Piping Fabrication = 58,000 inch diameter
Number of Direct Man Power at Peak in this Project was: 650
|