Ongoing Projects

Completed Projects

South Pars Gas Field Development - Phases 9 and 10
NGL 1200, 1300
Amir Kabir Petrochemical Complex
Sixth Olefin Plant
Bandar Abbas Refinery
Gas Compressor Stations S1, S2, S3, S6
Karanj - NGL 1500
Karanj Parsi - CS 600, 700
» Tabriz Petrochemical Complex
Khorasan Petrochemical Complex
Esfahan Lube Oil Complex
Sirri Island Gas Gathering and NGL Recovery
 Tabriz Petrochemical Complex

  • RAW WATER/ DEMINERALIZED WATER/ ANTS.
  • CIVIL AND CONSTRUCTION WORK OF AREA “C1” OF PRODUCTION LINE“C”/ UNIT 21 OF ETHYL BENZENE AND UNIT 22 OF STYRENE MONOMER UNITS.

» TABRIZ PETROCHEMICAL COMPLEX- RAW WATER/DEMINERALIZED WATER/POTABLE WATER TREATMENT

LOCATION  TABRIZ / IRAN
CLIENT TABRIZ PETROCHEMICAL COMPANY 
CONTRACTOR OIEC
CONTRACT EFFECTIVE DATE  SEPTEMBER 1995
CONTRACT DURATION  16.5 months (INCLUDING 2 months FOR MOBILIZATION)
BUDGETED man-hours 226,000 man-hours
EXPENDED man-hours 416,000 man-hours
PROGRESS STATUS COMPLETED (JANUARY 1997)
   

Scope of Work

- Erection of Mechanical Equipment
- Installation of A/G Piping
- Electrical Work
- Instrumentation
- Painting & Insulation
- Pre-commissioning

Major items of this Project were:

Erection of Mechanical Equipment 534 tons
Insulation 2,873 m2
Electrical & Instrumentation (Cabling)  76,000 l.m(length-meters)
Fabrication of Carbon Steel Pipes  14,000 inch diameter
Erection of Carbon Steel Pipes 13,000 inch diameter
Fabrication of Stainless Steel Pipes    13,000 inch diameter
Erection of Stainless Steel Pipes     7,500 inch diameter
Electrical Plates     35 units
Instrumentation Devices    410 units
Painting   5,085 m2

Number of Direct Man Power at Peak in this Project was: 200

» TABRIZ PETROCHEMICAL COMPLEX-CIVIL AND CONSTRUCTION WORK OF AREA “C1” OF PRODUCTION LINE  “C”/UNIT 21 ETHYL BENZENE AND UNIT 22 STYRENE MONOMER UNITS

LOCATION TABRIZ / IRAN
CLIENT TABRIZ PETROCHEMICAL COMPANY
CONTRACTOR OIEC
CONTRACT EFFECTIVE DATE JULY 1994
CONTRACT DURATION 43 months (INCLUDING 2 months FOR MOBILIZATION)
BUDGETED man-hours 1,814,540 man-hours
EXPENDED man-hours  3,700,580 man-hours (Direct); 4,972,760 man-  hours (Overall)
PROGRESS STATUS COMPLETED (MARCH 1998)
   

Scope of Work:

- Erection of Mechanical Equipment
- Installation of A/G Piping
- Electrical Work
- Instrumentation
- Painting & Insulation
- Pre-commissioning

Major items of this Project were

  • Excavation  = 52,000 m3
  • Reinforced Concrete Work  = 13,000 m3
  • Fabrication and Erection of Steel Structure = 1,050 tons
  • Erection of Mechanical Equipment   = 2,200 tons
  • Instrumentation (Cabling & Control) = 133 km
  • A/G Piping Erection  = 150,000 inch meter (in-m)
  • A/G Piping Fabrication   =  58,000 inch diameter

Number of Direct Man Power at Peak in this Project was: 650