South Pars Gas Field Development – Phases 9 & 10
The phases 9 and 10 of South Pars gas field are designed to produce 2MMMSCFD of natural gas as well as gas condensate, ethane, butane and propane (LPG) and sulfur.
Offshore facilities include two gas production platforms with 24 gas wells, two 32” subsea pipelines for transferring gas to the onshore refinery and two 4” pipelines for transferring glycol. This project was awarded to OIEC, the first local EPC contractor. The onshore part was an ignition to Mega projects in OIEC.
Picture Gallery
Location | Assalluyeh, Persian Gulf / Iran |
Client | Pars Oil and Gas Company (POGC) |
Partners | GS (South Korea) Iranian Offshore Engineering and Construction Company |
OIEC Scope (Onshore) | Engineering (FEED and detailed design) Procurement (supply of the equipment and bulk items, procurement services) Construction (site preparation, plant construction and erection) Commissioning (pre-commissioning, commissioning and start-up) Tail Gas Treatment Unit (TGTU) |
Products | Natural Gas: 50 million m3 per day Stabilized Condensate: 80,000 barrels per day LPG: 2,900 tons per day Ethane: 2,750 tons per day Sulfur: 400 tons per day |